The City of Minot has released the status of road projects in the city that will be continuing this week.

Sixth Street Underpass Project: The entrance on the south side of City Hall is now closed as work progresses up the hill on Sixth Street South. All employees and visitors to City Hall and the police station need to use the entrances on Second Avenue. Also, the detour remains in effect. Second Avenue will continue to be closed to through traffic in sections. The original detour route continues to be temporarily modified to reflect the construction at the 16th Street and Burdick Expressway intersection. Motorists should be aware that Maple Street is now open as work has been completed at the railroad crossing quiet zone project.

13th Street Southeast closed from approximately 21st Avenue Southeast to 37th Avenue Southeast: The intersection of 31st Avenue with 13th Street remains closed. Upon its reopening, the intersection of 37th Avenue and 13th Street will close. The intersection of 34th Avenue with 13th Street is and will remain accessible in the upcoming weeks. The project is behind schedule.

Emergency repair project: Numerous roadways around Minot have been worked on with this project. Work has included mill and overlays, curb repairs, patching, etc. The project is on schedule, with mainly punch list items remaining after Oct. 1. The sheer volume of work has pushed the project throughout the construction season.

Other emergency repair projects include:

16th Street Southwest at Burdick Expressway: Head to head traffic remains. Congestion seems to have lightened considerably since the west side of the project has been completed.

Fourth Avenue/Railway Avenue: Between Broadway and 27th Street, expect lane closures and delays in the upcoming weeks.

West Burdick: Expect interim lane closures and delays in the area in the upcoming weeks.

Street improvements (annual project): Numerous areas were planned for this construction season from mill and overlays to chip seal districts. The sheer volume of work pushed the project throughout the construction season.

24th Avenue Southwest from 16th Street to Dakota Loop: Work on 24th Avenue Southwest may continue partially into this week.